Engineering, FAT & Commissioning

Testing is where a control project either de-risks itself or postpones its problems to site. A defect found at FAT costs a bench hour. The same defect found during commissioning costs a crew, a crane and a day of plant time.

What we run

ActivityWhereWhat it proves
Point-to-point testWorkshopEvery terminal matches the loop drawing
Internal pre-FATWorkshopThe system is actually ready to be witnessed
Witnessed FATWorkshopClient signs off against an agreed protocol before shipment
SATSiteThe system survived shipping and installation
Loop checkingSiteField device to operator graphic, loop by loop
Startup supportSiteEngineers on hand while the plant takes the system

How a FAT protocol is built

An agreed protocol is what separates a test from a demonstration. We write it from the I/O schedule and the functional specification, and we send it before the test — not on the morning of.

SectionContent
HardwarePower-up, redundancy switchover, network fault injection, card removal and replacement
I/OEvery point exercised and observed at the graphic
LogicInterlocks, sequences and permissives driven through their trip conditions
AlarmsPriority, limits and annunciation behaviour
GraphicsNavigation, faceplates, trend and historian links
Failure casesWhat the system does when something is unplugged

Punch list discipline

CategoryMeaningEffect on sign-off
ABlocks shipmentMust be closed before the cabinets leave
BDoes not block shipment, must close before SATTracked with an owner and a date
CCosmetic or documentationClosed with the as-built handover

Categories are agreed with the client before the test starts. Deciding what counts as an A while standing in the workshop is how FATs turn into arguments.

What you get on handover

DocumentContents
FAT reportSigned protocol with per-case results and the punch list at close
SAT reportSite verification, deviations from FAT, resolution record
Loop check sheetsOne line per loop, signed by both parties
As-built drawingsMarked up during commissioning, reissued after startup
Configuration backupRestorable archive, plus a record of every change made on site

Scope boundary

IncludedNot included
Configuration, testing, loop checking, startup supportField instrument calibration and installation
Test protocols and all test documentationProcess commissioning and plant operation
Defect resolution within our scopeThird-party package defects — we log and escalate them

Bring us in before the hardware ships

The cheapest time to add a testing scope is before manufacture is finished, not after the cabinets are on a boat. Contact us.

Bring us in before the hardware ships

The cheapest time to add a testing scope is before manufacture finishes, not after the cabinets are on a boat.